Night Work Results in Closure, Detour Uses Carlisle & Carriage Way

Be advised that night work will take place on Deerfield Road this Wednesday through Friday night (October 5-8) beginning at 8 p.m. through 5 a.m.

This work will result in a detour of Deerfield Road. The detour route for both east and west bound traffic will use Carriage Way and Carlisle as reflected in the map provided below.

The contractor will continue to have two crews working overnight performing storm sewer and sanitary sewer work on the north lanes. This work is allowing the project to make up lost time and will help identify any underground utility conflicts sooner, providing more time for relocations to be completed before they impact progress.

Detour signage will be installed on a nightly basis for motorists to follow. All work and detours will be completed each morning by 5 a.m.

CONSTRUCTION FORECAST 2 deerfield rd NIGHT CLOSURE access CARRIAGE WAY BRIDGE

OVERALL PROGRESS: 98% Completed

98%